Williams
Communications – Tulsa, OK
1998 – Present
- Houston – Atlanta: Recreate over 570 drawings
along Transco Pipeline Route. Project length approximately
711 miles. Rebuilt landbase with ownership, showed as-built
locations to existing pipelines and all as-built data for
2 fiber optic cables.
- Kansas City – Chicago: As-built mapping of
various road routes to Chicago P.O.P. site. Route was approximately
215 miles in length.
- Doraville, GA: As-built mapping
- Jacksonville, FL Interconnect: As-built mapping
- Nashville - Cincinnati: As-built mapping
- Peoria, IL - Chicago: As-built mapping
- Transco II Overbuild
- Blacksburg, SC to China Grove, NC:
Mapping and survey of 80 miles along railroad right-of-way
and 9 miles of Road Build
- Charlotte, NC: Mapping and survey
8 miles of Metro Build
- Houston, TX: Mapping and survey 10
miles City of Houston Metro Build
- Doraville, GA: Mapping and survey
9 miles of Metro Build
- Interconnects (various locations):
Provide mapping and survey for interconnects of various
lengths in the following cities:
- Denver, CO
- Lubbock, TX
- Amarillo, TX
- Wichita Falls, TX
- San Antonio – El Paso: Provide As-built
drawings from field inspection reports and red-lined drawings
- Huntington, PA to Herndon, VA (Washington,
DC): Mapping, survey and right-of-way of approximately
250 miles, utilizing railroad, public and pipeline rights-of-way.
Approximately 200 miles located on Norfolk Southern/T-Cubed
right-of-way
- Puyallup to Seattle: Mapping and survey
approximately 40 miles utilizing public rights-of-way.
Provide utility research, prepare permit and construction
drawings.
- Atlanta to Chicago: Mapping and survey
for a segment from Tennessee/
Kentucky state line to Louisville, KY, approximately 200
miles in length, utilizing public right-of-way, railroad
right-of-way, and pipeline right-of-way.
- Segment from Louisville, KY to Cincinnati,
OH approximately 100 miles in length, utilizing public right-of-ways,
railroad right-of-ways, and pipeline right-of-ways.
- Segment from downtown Atlanta POP to a point
approximately 20 miles out from POP site. Public right-of-way
entire route.
- Houston to Los Angeles: Mapping and
survey for a segment from San Antonio to El Paso, TX. Route
approximately 530 miles in length, utilizing Interstate
I-10 and I-20. Route abandoned due to Texas D.O.T. New
route selected by Williams Co. utilizing right-of-way along
U.S. Hwy 90 and Union Pacific Railroad for route between
San Antonio and El Paso. Route consisted of approximately
552 miles.
- New Orleans to Tallahassee: Mapping
and survey for project segment from Mississippi/Alabama
state line to Alabama/Florida state line, approximately
90 miles.
- Mapping and survey of a 40 mile segment from
DeFuniak Springs to Ebro, Florida.
- Prepared Corps of Engineers drawings and drawings
for state-owned waters in the State of Louisiana.
- Miami to Tallahassee: Mapping and survey
for a segment from Tallahassee to Perry, Florida. Route
approximately 90 miles in length.
- Houston, TX to Manassas, VA: Posting
of as-built fiber optic information, approximately 1,300
miles along Transco Pipeline right-of-way.
- As-built mapping of 19 miles of fiber optic
cable located in metropolitan Houston.
- As-built mapping of fiber optic routes at Atlanta,
GA, Spartanburg, SC, Butler, AL, and Liberty, TX, totaling
approximately 82 miles.
CommTech Engineering
- Brookhaven, MS
- 190 miles of preliminary survey and mapping of Fiber Route
in Maryland, Delaware and Pennsylvania for AT&T and
PF Net joint build, utilizing existing AT&T right-of-way
and public right-of-way.
Schmidt Consulting
- Scottsdale, AZ
1998
- Prepared legal plats for site acquisition for approximately
25 cellular tower sites in and around Salt Lake City, UT.
Enbridge Energy– Duluth,
MN
(formerly Lakehead Pipeline Co.)
January 2002 - Present
- Terrace III Expansion – Construction staking and
as-built survey of 110 miles of 36” pipeline. Route
consisted of five separate loops between Clearbrook, Minnesota
and Superior, Wisconsin. The 110 miles was broken into five
segments:
- Clearbrook 30.65 miles
- Cass Lake 20.24 miles
- Deer River 25.09 miles
- Floodwood 15.66 miles
- Wrenshall 18.06 miles
Reliant Energy Field Services
Reliant Energy Gas Transmission Co.
2001 – Present
- Preliminary survey and mapping for various pipeline projects
ranging from compressor site to major transmission lines.
Mapping includes all permit drawings, legal property plats
and alignment sheets.
Williams Energy Group - Tulsa, OK
August 1999 - Present
- Preliminary mapping of Aspen Pipeline, a 240-mile pipeline
in the state of Utah utilizing automated alignment sheet
generation.
- Relocation of pipelines due to new road and highway construction
projects. Project locations in various parts of the United
States.
Dynegy Midstream Services, L.P. -
Houston, TX
1997 - Present
- North Versado GIS: Convert and develop Arcview
GIS System Map of 2700+ miles of gas gathering lines utilizing
aerial photography in SE New Mexico.
- Lake Charles GIS: Convert and develop Arcview GIS
System Map of 500+ miles of gas gathering lines in Louisiana.
- Lake Charles: GPS surveying and mapping of 110
miles of various pipelines located in Sabine Refuge area.
- Versado GIS: Convert and develop Arcview GIS System
Map of 1700+ miles of gas gathering lines utilizing aerial
photography in SE New Mexico.
- T-4 Permit Submittal: Prepared T-4 Permit Drawings
for Texas Railroad Commission of Gas Gathering Systems located
in Texas and performed updates to systems as needed.
Chico
E. Texas
Kellerville
LeFors
Monument
Myrtle Springs
Puckett
Shackelford
Sherman
Waskom |
1,428 miles
164 miles
404 miles
275 miles
41 miles
312 miles
28 miles
1,962 miles
230 miles
39 miles |
- Provided mapping and aerial photography for 300+ miles
Gas Gathering and Transmission Lines located in Texas and
Louisiana.
- Provided mapping and aerial photography for approximately
53 plant sites ranging from 2 mile radius to 7 mile radius
for risk management program.
- Mapping and GPS survey of a 230+ mile Gas Gathering System
located in and around Sherman, Texas. This was a pilot program
for GIS System for corporate rollout.
- Assisted in development of radius of exposure plan for
H2S pipeline located in East Texas. Obtained latitude and
longitude for all homes and business located within the
radius of exposure. Radius of exposure along route encompassed
an area approximately 21,000 ft. either side of route. Prepared
LEQ maps showing house locations and numbers that are linked
to 911 emergency call system. Established 911 call areas
and traffic control points for emergency response. Provided
and incorporated aerial photography for mapping and house
locations.
Superior Pipeline Company - Tulsa,
OK
2000
- Development of proposed Systems Map located in SE Oklahoma.
OneOK Texas Field Services - Tulsa,
OK
2000 - Present
- Remap ONEOK Gas Gathering Systems in Texas, Oklahoma and
Kansas containing over 17,000 miles of pipelines and gathering
lines.
- Provide Texas Railroad Commission T-4 Permit Drawings
for systems located in Texas Panhandle.
- Remap and combine ONEOK Gas Gathering Systems in the State
of Texas.
Sulphur River Pipeline - Edgewood,
TX
2000
- Update of H2S Radius of Exposure plan for H2S System located
in East Texas.
Grand River Dam Authority
– Pryor, OK
August 2002 - Present
- Preliminary survey and mapping for 2 power transmission
lines located in Washington County, Oklahoma. Project located
within state and county right-of-ways.

|